When performing a system upgrade we ensure that your production downtime is reduced to the bare minimum, and that you don’t suffer any production losses. We follow a fixed methodology for every retrofit project. This means we can perform the upgrade quickly and with little disturbance.
The cornerstones of our retrofit methodology include the following points:
-
a clear conversion plan beforehand
-
an analysis of all activities, possible consequences and risks, with risk-limiting procedures and fall-back scenarios
-
strict execution planning
-
simultaneous use of old and new controls during the conversion
-
return to the old control within four hours in the event of any unforeseen circumstances
-
all functions tested off-line beforehand
-
switchovers performed during weekends and holiday periods to the maximum extent possible to avoid loss of production